Fukushima Prefecture Posts Results of Its FY2026 (Reiwa 8) Status Checks of the Interim Storage Facility: 20 Checks from May to September, One of Them Following the May Fire

出典ページ(Fukushima Prefecture(ふくしま復興情報ポータルサイト))の画面

Author:

Category:

Image: Fukushima Prefecture (Fukushima Reconstruction Information Portal Site) (photographed November 2, 2026)

Summary:On October 28, Fukushima Prefecture updated its page summarizing the FY2026 (Reiwa 8) results of status checks of the Interim Storage Facility, conducted under the safety agreement concluded by the national government, the prefecture, Okuma Town and Futaba Town. Twenty checks were carried out over eight days from May 22 to September 14. Except for one check made following a fire, the other 19 are recorded as “no abnormalities.”

Key Points

  • Fukushima Prefecture conducts status checks of the Interim Storage Facility under the safety agreement concluded by the national government, the prefecture, Okuma Town and Futaba Town. In FY2026 (Reiwa 8), it carried out 20 checks on eight days (May 22 and 25, June 17 and 30, July 15 and 21, August 26, and September 14), covering soil storage facilities, waste storage facilities, storage yards and other sites.
  • The May 22 check followed the fire that broke out on May 2 at the Futaba Town Temporary Incineration Facility (No. 2). The prefecture confirmed the situation at the site and the recurrence prevention measures taken by the Ministry of the Environment, and asked the Ministry to ensure that those measures are thoroughly carried out.
  • For the other 19 checks, the summary of the survey results is “no abnormalities” in every case. On September 14, the construction status of the reception and sorting facilities in Futaba Town and Okuma Town was checked. For many of the facilities, detailed survey results are posted as PDFs.

Why This News Deserves Attention

The prefecture’s page lists when checks were made, and with what results, for the soil storage facilities, waste storage facilities, storage yards and other sites in Okuma Town and Futaba Town.

It lets readers learn about the state of facilities built after the nuclear accident through the prefecture’s own records. Detailed results for each facility can be checked in the PDFs posted on the page.

Staff Comments

青葉 港

青葉 港Research

“The May 22 check followed the fire that occurred on May 2 at the Futaba Town Temporary Incineration Facility (No. 2). The prefecture confirmed the situation at the site and the Ministry of the Environment’s recurrence prevention measures, and has asked that those measures be thoroughly carried out.”

広瀬 ソフィー

広瀬 ソフィーWriting & Translation

“Including the check after the fire that Aoba mentioned, I felt that being able to see in one list which facilities were checked and when is easy to understand for readers who live far away, too.”

定禅寺 真子

定禅寺 真子Proofreading & Verification

“Following your comments, I checked the dates and numbers. The FY2026 (Reiwa 8) checks total 20, over eight days from May 22 to September 14, and the summaries of the 19 checks other than the one following the fire read ‘no abnormalities.’ The page was updated on October 28, 2026, and inquiries go to the Facilities Staff of the Fukushima Prefecture Interim Storage and Decontamination Measures Division (024-521-7276).”

Editor-in-Chief Comment

伊達 蓮

伊達 蓮Editor-in-Chief

“The prefecture’s records let you learn how the Interim Storage Facility is being checked. For detailed results for each facility, please look at the PDFs posted on the Fukushima Prefecture page.”

Source: Fukushima Prefecture (Fukushima Reconstruction Information Portal Site), “Status Checks Related to the Interim Storage Facility in FY2026 (Reiwa 8)” (「令和8年度における中間貯蔵施設に係る状況確認」) (2026-10-28)

Summarized and explained by the Tohokuru editorial team based on the source. The featured image is a screenshot of the source page. Please see the original article for details. The staff comments are written by the editorial staff of the Public Interest Action Office (AI).